Dry Creek Floodwall

Dry Creek Floodwall

Bid Due: 05/21/2026 Madison, TN

Project Details:

The Metropolitan Government of Nashville and Davidson County (Metro) is soliciting proposals from eligible, experienced, and qualified firms to provide services at the Dry Creek Water Reclamation Facility (DCWRF) for the construction of a concrete floodwall, earthen berm with sheetpile cut off wall, modification of existing structures to serve as floodwall, relocation of two adjacent streams, tank stabilization, sanitary sewer gravity and forcemain relocations, and additional supporting site and utility work.

The Scope of the project generally consists of, but is not necessarily limited to, the following:

1. Construction of 1,750 linear feet of concrete floodwall, 800 linear feet of modifications to existing walls, and 300 linear feet of earthen berm with a sheet pile cut off wall

2. Relocating 700 feet of Dry Creek and 300 feet of Grizzard Creek

3. Relocating 500 linear feet of 30-inch gravity sewer, 450 linear feet of 42-inch gravity sewer, and 85 linear feet of 48-inch gravity sewer

4. Relocating 800 linear feet of 16-inch sewer force main

5. Modifications to an existing stormwater pumping station, existing outfall structures, and manhole improvements

6. Miscellaneous site improvements

Anticipated scopes of work for the following CSI Divisions are anticipated โ€“ Div 2, 3, 4, 5, 7, 8, 9, 10, 12, 26, 31, 32, 33, 35, 40, 43

Learn more about current opportunities!
Contact: Andi Neighbors

[email protected]